March 2023 Box Hill Ausgrid substation to Vineyard Transgrid substation ABF

Installing “Air Blown Fibre “(ABF) from Box Hill Ausgrid substation to Vineyard Transgrid substation 7.2KM

Project Specifications

Client:

Endeavour Energy

Project Details:
  • Installing micro duct into a 32mm conduit for 7KM
  • Installing the “Air Blown Fibre “(ABF) into the micro duct 7.2 km
  • Splicing the ABF into the ground sensor at various locations
  • Testing the fibre links with an “Optical Time Domain Reflectometer” (OTDR) providing results to the client